The run-sheet standard

How a Linklamp visit runs: port photos, signoff, rollback

For deciding whether to trust someone you have not met with your client's closet. Everything below is how the visit is written into the proposal you approve.

Your engineer stays in charge

The visit runs on your bridge call: Teams, Zoom or a phone bridge. Your engineer opens the change, watches links come up, and says when the visit is done. The person on site does not configure, re-address or reboot anything your engineer has not asked for.

Photos the ticket can use

Every labelled port is photographed before anything moves and again after, with its label tape in frame. A photo without a label only shows cords; a photo with the label ties a port to a row of your map, so your engineer can check a repatch from the thread.

If your client already labels ports, their scheme goes on the tape. If not, we propose one: SW1-23 for switch 1, port 23; A-09 for panel A, port 9. It follows common TIA-606 practice, which is a voluntary standard, not a legal requirement.

SW1-23firewall uplink

Before
After

Proposed label, after common TIA-606 practice (voluntary). If your client already has a scheme, we use theirs. The tape is in frame in both photos, so the ticket shows which port moved where.

Rollback, when you want it

Say "keep the old switch mounted until signoff" and the replacement goes into a free rack unit beside it. If signoff fails, cords go back to the old switch, matching the before photos, and your engineer decides what happens next.

No port map? Trace first

Where labels are missing, the visit begins with a trace stage: each cord followed, both ends labelled, and the current port map written down. You get that map with the photos, and the repatch to your new layout can follow in the same window or a second one.

What lands in the ticket

Before and after photos of every labelled port, the traced map if there was one, the time on and off site, and close-out notes: anything unexpected, anything left as it was, and where the old switch went.

The example, step by step

The dental office swap from the front page: a 24-port PoE switch, a 24-row map, Dana on Teams.

The run-sheet

On siteDana, remote

  1. 01
    On site

    Arrive inside the client window; office manager has the key. Check in on the bridge on Teams.

    Dana, remote

    Dana joins on Teams and opens the change.

  2. 02
    On site

    Photograph the closet, then every labelled port before anything moves.

    Dana, remote

    Dana gets the before photos in the ticket thread.

  3. 03
    On site

    Unmount the old switch, mount the replacement in its place, power it.

    Dana, remote

    Dana confirms the new switch is up on management.

  4. 04
    On site

    Repatch row by row to your 24-row map.

    Dana, remote

    Dana watches links come up as cords move.

  5. SignoffDana confirms, remotely
    • phones 1-8 up and powered
    • APs 9-12 up and powered
    • workstations 13-20 have link
    • printer 21 has link
    • x-ray sensor PC 22 has link
    • firewall uplink 23 up

    Example: what your engineer checks. The lamps light here only to show the moment.

  6. 05
    On siteRollback, only if needed

    If signoff fails: remount the old switch and move the cords back, matching the before photos.

    Dana, remote

    Dana calls the rollback.

  7. 06
    On site

    Photograph every labelled port after; label the old switch and leave it on site. Leave close-out notes.

    Dana, remote

    Dana gets the after photos and notes for the ticket and closes the change.